This is the final burn down chart and as you can see on day 1 obviously the ideal and the actual will be the same but then on day 2 my ideal was on for 10 tasks but the my actual went down to 8 tasks instead. Then on day 3 I was expecting to have only 5 tasks left but instead I was able to finish 1 more task than expected and then by day 4 I was able to finish all of my tasks even though I expected I'd still have 2 tasks remaining.